Background

A new house block containing 310, 8.5m² cells, suitable for double occupation. The development also included: an additional 16 safer cells as part of a new healthcare facility which includes a dentist suite, pharmacy and consulting rooms, extensive training space in the links between the cell blocks, extensions to amenities, industries and visits buildings, refurbishment of the existing amenities, visits, services building, entry and kitchen buildings including the use of a temporary kitchen, relocation of an existing workshop, construction of a new workshop and the refurbishment of an existing cottage into a training facility, two new all weather pitches, a new 248 space visitors car p[ark, two extensions to the existing staff car park. The project involved 21 separate phased handovers.