Appointed as Quantity Surveyors by Aquila Holdings, for construction works on the Chelmsford Waste Transfer station we had a programme of 20 weeks for the project.
Works included construction of a 2,800m2 waste transfer and recycling building, concrete service areas, foundations for weighbridges and offices and a section of access link road to the facility.
The project was on time and within budget, after 19 weeks, completing one week early.